Add tasks

  1. Select View > Gantt Chart.

  2. Type a name in the first empty Task Name field at the bottom of the task list, and press Enter.

    Screenshot that shows a task list in the Gantt Chart.

Want more? If adding tasks one at a time starts to take too long, you can also:

Outline tasks

Indent and outdent tasks to show hierarchy — that is, to turn your task list into an outline of your project. An indented task becomes a subtask of the task above it, which becomes a summary task.

  1. Select View > Gantt Chart.
  2. In the Task Name column, select the task you want to indent.
  3. Select Task > Indent Task Indent Task button in the ribbon. . The task becomes a subtask.
  4. Select Outdent Task Outdent Task button on the ribbon. to move the task back to the level of the task above it. It’s no longer a subtask.
    A task list with summary tasks and subtasks in the Gantt Chart

Want more?Use subtasks and summary tasks to show phases, easily navigate through a large project, and more.

You can link any two tasks in a project to show their relationship (also called a task dependency). Dependencies drive the project schedule — once you link the tasks, every change you make to one affects the other, which affects the next one, and so on.

  1. Select View > Gantt Chart.
  2. Hold down Ctrl and select the two tasks you want to link (in the Task Name column).
  3. Select Task > Link the Selected Tasks Link Tasks button on the Task tab of the ribbon .
    Three linked tasks on a Gantt Chart

Want more? Project supports four kinds of task links to show different relationships. Want to change the link type or remove the link completely?

Change your view

Project starts you off with the tried-and-true Gantt Chart, but you have dozens of other options for viewing your tasks and resources and how they’re all connected. You can change any view to meet your specific needs.

  1. Select the View tab.
  2. In the Task Views group or Resource Views group, select the view that you want to use.
  3. To see all the available views, select Gantt Chart > More Views, and then choose from the options in the More Views dialog box.

Task Views group on the ribbon and part of a sample Network Diagram

Want more? There’s a lot more to learn here! Need some help choosing the right view of your project?

Printing a view or report in Project is similar to printing in other Office programs:

Select File > Print > Print.

Print button and print options in the backstage